Check and validate a high voltage switching program
You are an authorised Switching Program Checker in the network operations centre.
What has happened
Network Controller Ana Kovac has written switching program SP-26-0921 for the BUN-12 outage on Tuesday 16 September to replace pole 119. The program has eighteen steps: it transfers load to feeder BUN-14 by closing ABS-130, opens ABS-118 and ABS-122 to isolate the section, proves de-energised and applies earths at poles 118 and 122, then issues access authority EAA-26-2210 and restores in reverse. The network diagram shows a 22 kV spur to a dairy substation between poles 120 and 121 with its own drop out fuses, and a recent operation record shows ABS-130 was left open for a fault last month. Customer notification says 8:00 am to 2:00 pm.
Deliverables
- Marked up copy of the switching program with your check on every step
- Switching program register entry with the validation decision and reasons
- Note to the controller summarising the findings
Documents to use
Systems to use
Switching Program Register
Records every distribution, substation and rail traction switching program from writing through validation, direction and completion, with the writer, checker, controller and each step's confirmation.
Access Authority and Permit Register
The operations centre record of every access authority, vicinity authority, test permit and rail traction access requested, issued and cancelled, with the isolation and earthing state confirmed.
Work Orders and Crew Allocation
Records every planned and reactive job on the networks with the client, apparatus, allocated crew, access requirements, hours worked and completion status.
Units of competency
Current on training.gov.au for the Transmission, Distribution and Rail Sector as at 10 September 2026.
UETDRIS023Develop and validate high voltage distribution switching programsUETDRIS021Coordinate and direct switching programsUETDRIS022Coordinate permit proceduresUETDRSO020Operate SCADA equipmentQualifications
UET40422Certificate IV in ESI - Network SystemsWhat to look for
Evidence guide
The student should find that the dairy spur between the earths is a possible back feed source that must be addressed, that the ABS-130 status must be confirmed before load transfer, and that the earth steps need pole numbers. Validation must be refused or conditional where any of these is unresolved. Look for a step by step trace on the diagram and clear reasons recorded in the register.