Plan a transmission tower climbing inspection and hardware replacement
You are a Transmission Line Worker and crew planner in Transmission Lines.
What has happened
The client has confirmed a two day outage of the Morwell to Hazelwood 220 kV line on 22 and 23 September for work order WO-26-4388. A ground inspection in July found corroded suspension hardware on phase A of structure 47 and missing cotter pins on phase C. The client's transmission control will perform the terminal switching; Gridworks must write the program for its own portable earths at structures 44 and 52 and request the access authority. The crew of six includes two climbers whose tower rescue currency expires on 20 September. A parallel 220 kV line on the same easement remains live throughout, and the structures are 42 metres high in open farmland with a farm access track.
Deliverables
- Job risk assessment with tower rescue plan and induced voltage controls
- Authorised persons check and rescue drill booking
- Completed switching program SP-26-0925 submitted for checking
- Access authority request in the register
- Work plan and materials list on the work order
Documents to use
Systems to use
Work Orders and Crew Allocation
Records every planned and reactive job on the networks with the client, apparatus, allocated crew, access requirements, hours worked and completion status.
Switching Program Register
Records every distribution, substation and rail traction switching program from writing through validation, direction and completion, with the writer, checker, controller and each step's confirmation.
Access Authority and Permit Register
The operations centre record of every access authority, vicinity authority, test permit and rail traction access requested, issued and cancelled, with the isolation and earthing state confirmed.
Pole and Asset Inspection Register
The record of every pole, structure, substation item and vegetation span inspected, with findings, residual strength, defect classification, priority and treatment.
Units of competency
Current on training.gov.au for the Transmission, Distribution and Rail Sector as at 10 September 2026.
UETDRTO005Inspect transmission structures, conductors and hardwareUETDRTO007Install and maintain transmission structures and hardwareUETDRMP020Perform tower rescueUETDREL005Work safely in the vicinity of live electrical apparatusQualifications
UET30521Certificate III in ESI - Transmission OverheadWhat to look for
Evidence guide
The risk assessment must treat induced voltage from the live parallel line as a hazard requiring working earths at the structure, and must include a credible tower rescue plan with current rescuers. Look for the rescue currency gap identified and resolved, a switching program that coordinates with the client's terminal switching, and an access request that bounds the work area by the portable earths.