Repair a low voltage underground cable fault and restore supply
You are a Cable Jointer authorised for low voltage polymeric cable in Underground Cables.
What has happened
A low voltage cable fault between pillars P-2231 and P-2232 in Albert Street, Sebastopol, work order WO-26-4402, has left six customers off supply since yesterday. The fault has been located 42 metres from P-2231 by pulse echo and the excavation is open, 1.2 metres deep, with a gas main marked within 500 millimetres on one side. Electrical access authority EAA-26-2204 is held by the Underground Cables Manager with earths E-14 and E-15 applied, and switching program SP-26-0918 has restoration steps 7 to 12 pending. The pillar P-2231 has heat damaged fuse carriers. The pit rescue kit is on site and the weather is fine.
Deliverables
- Completed job risk assessment for the excavation and pit rescue
- Work order entry with joint details and test results
- Asset inspection register entry for pillar P-2231
- Switching program register execution notes for restoration steps
- Updated access and permit register entry showing cancellation
Documents to use
Systems to use
Work Orders and Crew Allocation
Records every planned and reactive job on the networks with the client, apparatus, allocated crew, access requirements, hours worked and completion status.
Access Authority and Permit Register
The operations centre record of every access authority, vicinity authority, test permit and rail traction access requested, issued and cancelled, with the isolation and earthing state confirmed.
Switching Program Register
Records every distribution, substation and rail traction switching program from writing through validation, direction and completion, with the writer, checker, controller and each step's confirmation.
Pole and Asset Inspection Register
The record of every pole, structure, substation item and vegetation span inspected, with findings, residual strength, defect classification, priority and treatment.
Units of competency
Current on training.gov.au for the Transmission, Distribution and Rail Sector as at 10 September 2026.
UETDRDU017Locate faults in underground power cablesUETDRDU015Joint, terminate and maintain low voltage underground polymeric cableUETDRDU002Inspect underground electrical apparatusUETDRMP014Perform cable pit/trench/excavation rescueUETDRMP001Apply access authority procedures to work on or near electrical apparatusQualifications
UET30821Certificate III in ESI - Distribution UndergroundWhat to look for
Evidence guide
The student must confirm the earths and spike the cable before cutting, treat the gas main and the excavation depth as controlled hazards with a rescue plan, and record test results as measured values. Restoration must follow the program sequence after cancellation of the authority with read backs recorded. Look for consistent records across the work order, the access register and the switching register.