Run a night possession on the 1,500 volt traction overhead
You are a Rail Traction Line Worker and possession lead in Rail Traction.
What has happened
A night possession on the Sunshine to Deer Park up line, work order WO-26-4377, runs from 0:30 am to 4:30 am on Saturday 13 September. The work is fourteen dropper replacements, a registration arm adjustment at structure 1226 and an inspection of the section insulator at structure 1231, in overhead wiring section 34. Traction switching schedule TS-26-0187 is validated and rail traction access RTA-26-0442 is requested. Track protection is provided by the rail operator. Last month a worker climbed a structure before the access was issued, recorded as INC-2026-046, and the Rail Traction Manager wants radio confirmation of the access to every crew member before anyone touches a structure. The down line remains live and trains may run on it.
Deliverables
- Possession briefing and job risk assessment
- Completed access form and access register entry with radio confirmation noted
- Switching program register execution record for TS-26-0187
- Work order with measurements and completion
- Asset inspection register entry for the section insulator
Documents to use
Systems to use
Access Authority and Permit Register
The operations centre record of every access authority, vicinity authority, test permit and rail traction access requested, issued and cancelled, with the isolation and earthing state confirmed.
Switching Program Register
Records every distribution, substation and rail traction switching program from writing through validation, direction and completion, with the writer, checker, controller and each step's confirmation.
Work Orders and Crew Allocation
Records every planned and reactive job on the networks with the client, apparatus, allocated crew, access requirements, hours worked and completion status.
Pole and Asset Inspection Register
The record of every pole, structure, substation item and vegetation span inspected, with findings, residual strength, defect classification, priority and treatment.
Units of competency
Current on training.gov.au for the Transmission, Distribution and Rail Sector as at 10 September 2026.
UETDRRT011Maintain traction overhead wiring systemsUETDRRT013Perform rail traction switching operations to a given scheduleUETDRRT009Maintain overhead traction components and equipmentUETDRRT014Test and verify rail traction installationsUETDRMP001Apply access authority procedures to work on or near electrical apparatusQualifications
UET30721Certificate III in ESI - Rail TractionWhat to look for
Evidence guide
Look for the possession, track protection, switching and access steps in the correct order, with the radio confirmation to every crew member recorded before climbing. The live down line must be treated as a controlled hazard. Measurements and the section insulator condition should be recorded, and the hand back should show earths removed, access cancelled and restoration switching complete within the possession window.